The
Central line is a
London Underground line, coloured red on
the
tube map. It is a deep-level "tube"
line, running east-west across London, and has the greatest total
length of track of any line on the Underground. Out of the 49
stations served, 20 are below ground. It is the second busiest line
on the Underground.
History
The beginnings
Although
the Central London Railway was incorporated in
1891 for a line between Shepherd's Bush
and Bank
(with an extension to Liverpool
Street
authorised in 1892) the time for completion had to
be extended twice (1894, 1899); and it was not until June 27, 1900
that it was formally opened, a month before public traffic began to
use the railway on July 30, to Bank station. The railway was
initially operated by electric locomotives hauling a train of
trailer cars. The distinctive station buildings, many of which
survive, were designed by the architect
Harry Bell Measures.
The railway has had a chequered history. Although the tunnels were
bored with the unusual diameter of 11 feet 8¼ inches (3.56m), they
were not well aligned and it was discovered that the rolling stock,
which was already smaller than would be expected for this size of
tunnel, would not fit. It is rumoured that the engineers forgot to
take into account the height of the rails above the tunnel floor.
The problem was remedied by a combination of replacing the
bullhead rail running rails with lower profile
bridge rails, and shortening the springs on the rolling stock. The
locomotives caused considerable problems with vibration as they
weighed 48
long tons (49 tonnes), most of
which was
unsprung.
In the late 1930s the tunnels were expanded and realigned and the
stations lengthened. In 1940, the line was converted to the
standard tube
four rail
electrification. Because of the manner in which tunnel had been
enlarged, it was no longer round and for clearance reasons the
positive rail within the original tunnels had to be of an unusual
shape with the top contact surface 40 mm (1½ inches) higher than
normal. This is still the situation today, and the extra height can
be observed at most deep-level stations, where the insulating
'pots' stand on small cement mounds.
Trains between
Liverpool
Street
and White City
must have special positive collectors that can lift
higher than normal. In turn the current Central line stock
cannot run on any other line, partly because they are operated by
Automatic Train Operation,
have no
trip-cocks, and would interfere
with other signalling equipment. There are also clearance problems
with the gearboxes.
One legacy
of the line's building is that the sections under the City
were built to follow the geography of the streets
above, rather than underneath buildings, to take advantage of the
free wayleave offered by the
government. As a result there are many sharp bends and
curves between St. Paul's
, Bank
and Liverpool Street
. At Bank station, the Central line platforms
are so tightly curved it is not possible to see one end of the
platform from the other and the traditional "
Mind The Gap" message is particularly stressed
here.
For several years from the outset a uniform fare of two pence was
adopted: the railway was popularly known as the "Twopenny Tube". In
July 1907 graduated fares of two pence and three pence were
introduced: a one penny fare was added in 1909.
Extensions of the line
- 1908:
- Extended in the west by means of a loop to
Wood Lane
Exhibition Station in 1908 for the Franco-British
Exhibition.
- 1912: Extended eastwards to
Liverpool
Street
.
- 1920: In the west, a short
connecting link was made from Wood Lane station to join the
Great Western Railway
(GWR)-operated line, the Ealing and Shepherd’s Bush
Railway, allowing trains to run to Ealing
Broadway
.
- 1935: As part of the New Works Programme 1935–40,
announced in June 1935, London Transport proposed works to extend
the Central line as follows:
- * "to
construct and electrify two additional GWR tracks from North
Acton
to Ruislip
, allowing
Central line trains from Wood Lane to use the line;
- :An
extension beyond West Ruislip to Harefield
Road
and Denham
was also planned (and shown on tube maps of the
period) but was abandoned, along with the Northern Heights
extensions of the Northern line, due
to post-war establishment of the Green
belt around London which restricted development of land in the
area.
- * "to
construct a tube railway in continuation of the Central London Line
from Liverpool
Street
eastwards to points where it will connect with the
Loughton
and Grange Hill
lines (probably near Leyton
and Newbury Park
so as to permit running through trains to stations
in the West End of
London
and beyond without passing over the congested LNER
(London and North
Eastern Railway) lines at Stratford
and Ilford
"
- WW2: Although the works of the latter were
completed by the outbreak of war the opening was delayed, and the
section, safer as it was from bombing, was used as a long, narrow,
munitions factory by the Plessey company.
- 1946-48: The eastern branch
opened in December 1946 as far as Stratford
(with trains continuing empty through the new tube
tunnels to a temporary reversing facility at Drapers Field, in the
cutting south of Leyton
), with the
line beyond Stratford opening as far as Woodford and Newbury Park
in 1947. As for the Fairlop
Loop, the southern link from Newbury Park
to Ilford
closed in
1947, whilst the connection to Seven Kings lasted until
1956. The Newbury Park to Woodford via Hainault section
opened to tube trains in 1948, as did the section from Woodford to
Buckhurst Hill. BR trains continued to access the line via a link
from Temple Mills East to Leyton. These included the BR locomotives and
stock for the Epping - Ongar shuttle (until electrification in
1957), freight trains to sidings (including Fairlop, Barkingside,
Buckhurst Hill, Theydon Bois, South Woodford, Loughton, North
Weald, and Ongar) until the mid-1960s, and early-morning and
late-night trains between Liverpool Street
and Epping
(latterly
formed by DMUs, and last running on May 31, 1970).
This
section of line now forms a loop and there are some through
services to Woodford
via Hainault
(and vice versa), every 20 minutes or
so.
- For
the western extension, a new pair of tracks for the Central line
opened from North Acton to Greenford
opened in 1947, with the section to West Ruislip
following in 1948. The powers to extend the line to Denham
were never implemented. The Great Western Railway's halts and
stations between Old Oak Common West junction and South
Ruislip
were all closed by 1948, with the shuttle to
Greenford using a bay in the new Underground station.
- 1949: Extended to Epping
, when London Transport took over the line from
British Railways.
- 1957: Extended from Epping
to Ongar
, taking over from British Railways.
Richmond extensions
In 1912
plans were published for an extension of the line from Shepherd's
Bush
under Goldhawk Road, Stamford Brook Road and Bath
Road to Turnham Green
and Gunnersbury
, including stations at Hammersmith Grove,
Paddenswick Road, Rylett Road, Stamford Gardens, Turnham Green and
Heathfield Terrace. This would have enabled the Central London
Railway to run trains through to Richmond
and possibly beyond. The route was
authorised in 1913Central London Railway Act, 1913 but work had not
started by the outbreak of
World War I
the following year.
In 1919 an alternative route was published,
building a tunnelled link to the disused London and South Western
Railway (L&SWR) tracks south of the L&SWR's Shepherd's Bush station
then via Hammersmith
station
and Turnham Green
. Although authorisation was granted in
1920,Central London and Metropolitan District Railway Companies
(Works) Act, 1920 the connection was never realised, and the
L&SWR tracks were eventually used by the Piccadilly line when it was extended west of
Hammersmith
in 1932. However the proposal has
occasionally reappeared.

A train of 1992 tube stock approaching
Roding Valley station on the Central line.

A 1992 tube stock train terminating
at Loughton Station.
Epping to Ongar branch
Although electrification of this section had begun under the
1935/40 New Works Programme (see above), the line remained
steam-hauled (though from 16-27 June 1952 an experimental ACV/BUT
three-car lightweight railcar set operated part of the shuttle
service Monday-Friday) until November 18, 1957. From that date
two-, three- and four-car tube trains were used on the branch.
Shorter
platforms at North Weald and Blake Hall, coupled with a limited
power supply, meant it was not possible to work through trains to
and from London
, and the
line remained a branch, though the shuttle service initially
operated between Ongar
and Loughton
. Expected levels of passenger use never
materialised; the line became a heavy loss maker, and was closed on
September 30, 1994 and sold to the Pilot Group. The direct
connection to Epping was lifted soon after closure, but the
remaining section of the branch stayed intact.
A
heritage passenger service owned by
Epping Ongar
Railway Ltd.
started operation in October 2004.
A train
runs on Sundays from Ongar to Coopersale, stopping at North Weald,
with a possible extension to Epping
in the future. It does not stop at
the old Blake
Hall station
, as the station platform was removed upon station
closure in 1981.
2003 derailment and closure
A Central
line train derailed at Chancery Lane
on January 25, 2003, injuring 32 passengers, after
a traction motor became detached from the train and fell onto the
track. The entire line was closed whilst the cause of the
failure was determined and appropriate modifications made to the
trains. The line was then re-opened in stages. By late March 2003 a
limited service was running on the eastern and western extremities
of the line, with the central section still closed. Services
resumed over that central section on April 3, 2003 and to all
stations (albeit at a reduced frequency) on April 12, with a full
service by the end of the month. The initial closure also extended
to the
Waterloo & City
line which uses the same "1992 tube stock" trains, but this
line, being far shorter - with only two stops and far fewer trains
- reopened quickly.
A more
minor derailment occurred on a set of points at the London end of
the westbound platform at White City
on May 11, 2004, but there were no reported
injuries.
2007 derailment
Three
carriages came off the rails on the westbound Central line between
Mile
End
and Bethnal Green
at about 0900 BST on July 5, 2007. The cause
was attributed to a roll of
tarpaulin
which came free from a storage location next to the lines.
London Fire
Brigade
sent 14 fire engines to the scene, including four
urban search and rescue
vehicles. The line was closed between Liverpool
Street
and Leytonstone
and re-opened on July 7, 2007.
Rolling stock
Former rolling stock
When opened in 1900, the railway was operated by electric
locomotives hauling coaches. The coaches were fitted with gates at
each end, similar to those used on the
City and South London Railway
and the
Glasgow Subway. The
locomotives, with a large unsprung weight, proved highly
unsatisafactory and the cause of considerable vibration. They were
replaced as early as 1903 with motor cars, with the existing
coaching stock being adapted to run as trailers within newly formed
electric multiple
units.
By the 1920s the rolling stock was in need of modernisation or
replacement. Given that the then-new
Standard Stock was too
large to work in the line's tunnels, it was decided to modernise
the existing fleet. The end gates were removed and replaced by an
extension to the passenger accommodation. Two air operated
single-leaf sliding doors were inserted into both sides of each
carriage.
Reconstruction work was carried out by the
Union Construction Company at Feltham
.
Additional trains were purchased for the
opening of the Wood Lane to Ealing Broadway
extension in 1920. These were also
temporarily used on the Watford extension of the
Bakerloo line.
The
1900/03 stock
and
1920 stock were
finally withdrawn from service in 1939. With the enlargement of the
tunnels and modification of the electrical supply, Standard Stock
(displaced from the
Northern line by
new
1938 Stock) was
operated - eventually as 8-car trains following platform
extensions.
The Standard Stock became increasingly unreliable during the 1950s.
Some had been stored during
World War
II pending the opening of extensions. Plans for replacement
(using a production version of the prototype
1960 Stock) were abandoned;
new trains of
1962
Stock (virtually identical to the tried and tested 1959 Stock)
were ordered instead. These operated until their replacement by
1992 Stock in the
early 1990s.
The Epping-Ongar branch was not electrified until 1957, prior to
which the service was operated on behalf of
London Transport by
British Railways using steam hauled
coaches. Upon electrification, two-car sets of
1935 Stock were initially
used, later replaced by 4-car sets of 1962 Stock specially modified
to cope with the limited current.
The section closed in 1994, and
eventually became a heritage railway now known as the Epping Ongar
Railway
.
Current trains

Interior of 1992 Stock used on the
Central line
In common with virtually all other Underground lines, the Central
line is worked by a single type of rolling stock.
The 1992 Tube Stock was introduced
gradually from April 1993 to February 17, 1995, and was the first
in London
to
introduce automated announcement of the next station and
connections available. The 1992 stock is painted in the
standard red, white and blue Underground livery and runs in 8-car
sets.
In 1996 the line was fitted with
Automatic Train Operation, and
this was brought into service in sections over the next few
years.
Map

The
TFL line diagram is available online.
Stations
In order from west to east.
| West Ruislip Branch |
| Station |
Image |
Opened |
Additional Information |
West Ruislip |
 |
November 21, 1948 |
Terminus Opened as West Ruislip (for
Ickenham); the suffix was later dropped. |
Ruislip Gardens |
 |
November 21, 1948 |
|
South Ruislip |
 |
November 21, 1948 |
|
Northolt |
 |
November 21, 1948 |
|
Greenford |
 |
June 30, 1947 |
|
Perivale |
 |
June 30, 1947 |
|
Hanger Lane |
 |
June 30, 1947 |
|
| Branch joins Central Branch at North
Acton |
| Ealing Broadway Branch |
Ealing Broadway ( Trains to Heathrow ) |
 |
August 3, 1920 |
Terminus |
West Acton |
 |
November 5, 1923 |
|
| Branch joins Central Branch at North
Acton |
| Central section |
North Acton |
 |
November 5, 1923 |
|
East Acton |
 |
August 3, 1920 |
|
White City |
 |
November 23, 1947 |
|
Shepherd's Bush |
 |
July 30, 1900 |
Refurbished in 2008 |
Holland Park |
 |
July 30, 1900 |
|
Notting Hill Gate |
 |
July 30, 1900 |
|
Queensway |
 |
July 30, 1900 |
Opened as Queens Road; renamed September 1, 1946 |
Lancaster Gate |
 |
July 30, 1900 |
|
Marble Arch |
 |
July 30, 1900 |
|
Bond Street |
 |
September 24, 1900 |
|
Oxford Circus |
 |
July 30, 1900 |
|
Tottenham Court Road |
[[Image:Tottenham Court Road stn main entrance |
July 30, 1900 |
Opened as Oxford Street; renamed March 9, 1908 |
Holborn |
 |
September 25, 1933 |
Opened as Holborn (Kingsway); the suffix was later dropped.
Opened as a Piccadilly station on
December 15 1906, but Central platforms opened September 25,
1933 |
Chancery Lane |
 |
July 30, 1900 |
Renamed Chancery Lane (Grays Inn) June 25, 1934; the suffix was
later dropped |
St. Paul's |
 |
July 30, 1900 |
Opened as Post Office; renamed February 1, 1937 |
Bank |
 |
July 30, 1900 |
|
Liverpool Street ( Trains to Stansted ) |
 |
July 28, 1912 |
|
Bethnal Green |
 |
December 4, 1946 |
|
Mile End |
 |
December 4, 1946 |
|
Stratford |
 |
December 4, 1946 |
|
Leyton |
 |
May 5, 1947 |
|
Leytonstone |
 |
May 5, 1947 |
|
| Central Branch splits into Epping and Hainault
Loop Branches |
| Epping Branch |
Snaresbrook |
 |
December 14, 1947 |
|
South Woodford |
 |
December 14, 1947 |
Opened as South Woodford (George Lane); renamed 1947 |
Woodford |
 |
December 14, 1947 |
Terminus of Hainault Loop |
Buckhurst Hill |
 |
November 21, 1948 |
|
Loughton |
 |
November 21, 1948 |
|
Debden |
 |
September 25, 1949 |
|
Theydon Bois |
 |
September 25, 1949 |
|
Epping , |
 |
September 25, 1949 |
Terminus |
| Hainault Loop |
Wanstead |
 |
December 14, 1947 |
|
Redbridge |
 |
December 14, 1947 |
|
Gants Hill |
 |
December 14, 1947 |
|
Newbury Park |
 |
December 14, 1947 |
|
Barkingside |
 |
May 31, 1948 |
|
Fairlop |
 |
May 31, 1948 |
|
Hainault |
 |
May 31, 1948 |
|
Grange Hill |
 |
November 21, 1948 |
|
Chigwell |
 |
November 21, 1948 |
|
Roding Valley |
 |
November 21, 1948 |
Currently least used station on the network |
| Trains join Epping Branch at Woodford and
'Terminate (except peak hours) |
.png/250px-Step-free_access_notification_(Central_line).png)
Notice explaining about step-free
access.
This can be found inside every Central line train.
Former Stations
Future plans
The
developers of the First Central business park at Park Royal
, West London were
planning a new station between North Acton
and Hanger Lane
. This would have served the business park and
provide a walking distance interchange with Park
Royal
station on the Piccadilly line. This is not
currently being actively pursued.
If the
Chelsea-Hackney line is
built then it is intended that it will take over the Epping branch
of the Central line. Current hopes are that this will be completed
by 2025.
It would
be possible to provide an interchange with London Overground at Shoreditch High Street
station which is due to open in 2010 but current
thinking is that the disadvantages to existing passengers outweigh
the benefits.
References
- First
Central Business Park
- Crossrail official site
- PDF on the route options
External links