Copenhagen Metro ( ) is a
rapid transit serving Copenhagen
, Frederiksberg
and Tårnby
in
Denmark. The system opened between 2002 and 2007, and has
two lines,
M1 and
M2.
The driverless light metro supplements the larger S-train rapid transit system, and is integrated with
DSB
local trains and Movia
buses. Through the city center and west to Frederiksberg,
both lines share a common line.
To the south-east the system serves Amager
, with the M1
running the new neighborhood of Ørestad
, and the M2
serves the eastern neighborhoods and Copenhagen Airport
. The metro has 22
stations, of which 9 are
underground. In 2008, the metro carried 47 million
passengers.
The system is owned by Metroselskabet, that is again owned by the
municipalities of Copenhagen and Frederiksberg, and the
Ministry of Transport. The 34
trains are of the class
AnsaldoBreda Driverless Metro,
and stationed at the Control and Maintenance Center in Vanløse.
They are wide and three cars long; their power output is supplied
by a 750-volt carrying
third rail.
Operation of the system is subcontracted to Metro Service. Trains
run continually, including all night, with
headway varying from two to twenty minutes.
Planning of the metro started in 1992 with the development plans
for Ørestad. A
tramway and
light rail were considered, but discarded in the
process.
Construction started in 1996, and stage 1,
from Nørreport
to Vestamager
and Lergravsparken
, opened in 2002. Stage 2, from
Nørreport to Vanløse
, opened in 2003, followed by stage 3, from
Lergravsparken to Lufthavnen
, in 2007. Construction of the
City Circle Line is underway, and is
planned to open in 2018. It will form a circle around the city
center, be entirely underground and not share any track with M1 and
M2.
A
further expansion towards Brønshøj
is being considered.
History
Background
The
background for the metro was the urban development of the Ørestad
area of Copenhagen. The principal of
building a rail transit was passed by the Parliament of
Denmark
on 24 June 1992, with the Ørestad
Act. The responsibility for developing the area, as
well as building and operating the metro, was given to the
Ørestad Development
Corporation, a joint venture between Copenhagen Municipality
(45%) and the
Ministry of
Finance (55%). Initially, three modes of transport were
considered: a
tramway, a
light rail and a rapid transit. In October 1994,
the Development Corporation chose a light rapid transit
system.
The tram solution would have been a street tram system that
operated on the regular streets, without any major infrastructure
investments in the city center, such as right-of-way. Through
Ørestad it would have level crossing, and only with the
European Route E20 and the
Øresund Line would there be a
grade-separated crossing. It would have a driver and operate at
about a 150-second interval, about twice the cycle time of the
city's traffic lights. Power would have been provided with
overhead wire. Stops would be located about
ever and be at street level. The articulated trams would have been
about long and have a capacity of 230 passengers.
The light rail model would have used the same approach as the tram
in Ørestad, but would instead have run through a tunnel in the city
center. The tunnel sections would be shorter, but the diameter
larger because it would have to accommodate overhead wires. The
system would have the same frequency as the tram, but use double
trams and would therefore require larger stations. The metro
solution was chosen because it combined the highest average speeds,
the highest ridership, the lowest visual and audio impact, and the
lowest number of accidents. Despite it also bearing the highest
investments, it had the highest
net
present value.

Crossing from elevated railway to
tunnel near Islands Brygge
The decision to build stage 2, from Nørreport to Vanløse, and state
3 to the airport, was made by parliament on 21 December 1994. Stage
2 involved the establishment of the company
Fredriksbergbaneselskapet I/S in February 1995, owned 70% by the
Ørestad Development Corporation and 30% by Fredriksberg
Municipality. The third stage would be built by
Østamagerbaneselskapet I/S, established in September 1995 and owned
55% by the Ørestad Development Corporation and 45% by
Copenhagen County. In October 1996, a
contract was signed with the Copenhagen Metro Construction Group
(COMET) for building the lines, and with
Ansaldo for delivery of the trains and operate the
system the first five years. COMET is a consortium comprised
Astaldi,
Bachy,
SAE,
Ilbau, NCC
Rasmussen & Schiøtz Anlæg and
Tarmac
Construction.
Construction
Construction started in November 1996, with the moving of
underground pipes and wires around the station areas. In August
1997, construction started at the depot, and in September, COMET
started the first mainline construction work. In October and
November, the two
tunnel boring
machines (TMB), christened Liva and Bette, were delivered.
They
started digging each barrel of the tunnel from Islands
Brygge
in February 1998. The same month, the
Public Transport
Authority gave the necessary permits to operate a driverless
metro.
The section between Fasanvej
and Frederiksberg
is a former S-train line, and was last operated as
such on 20 June 1998.
The first section of tunnel was completed by September 1998, and
the TMBs moved to Havnegade. By December 1998, work had started on
all the initial nine stations. Plans for M2 were presented to the
public in April 1999, with a debate emerging if the proposed
elevated solution is the best. In May, the first trains were
delivered, and trial runs began at the depot. In December, the
tunnels were completed to Strandlodsvej, and the TMBs were moved to
Havnegade, where they started to grind towards Frederiksberg.
From 1
January 2000, the S-train service from Solbjerg
to Vanløse was terminated, and work to rebuilt to
metro started. By February 2001, all tunnels were
finished.
In March 2001, Copenhagen County Council decided to start
construction of stage 3. On 6 November 2001, the first train
operates through a tunnel section. On 28 November, laying of tracks
along stage 1 and stage 2A completed. An agreement about financing
stage 3 was reached on 12 April. By 22 May, the 18 delivered trains
had test-run . The section from Nørreport to Lergravsparken and
Vesterport was opened on 19 October 2002. Initially, the system had
a 12-minute
headway on each of the two
services. From 3 December this was reduced to 9 minutes, and from
19 December to 6 minutes. Operation of the system was subcontracted
to Ansaldo, who again subcontracted it to Metro Service, a
subsidiary of
Serco Group. The contract
had a duration of five years, with an option for extension for
another three.
M1 and M2
Trial runs on the next section of metro, stage 2A from Nørreport to
Frederiksberg, began on 24 February. It opened on 29 May 2003. All
changes to bus and tin schedules in Copenhagen took place on 25
May, but to allow
Queen
Margrethe II to open the line, the opening needed to be adapted
to her calendar. This caused four days without a bus service along
the line. Stage 2B, from Frederiksberg to Vanløse, opened on 12
October.

Elevated station on Amager
Forum Station
was nominated for the European
Union Prize for Contemporary Architecture in 2005. On 2
December 2005, the final agreement to build the City Circle Line
was made between the local and national governments. The price was
estimated at
DKK 11.5 to 18.3
billion, of which DKK 5.4 billion will be financed though
ticket sales, and the remaining from the state and municipalities.
In 2006, it was announced that the contract with Ansaldo to operate
the metro had been prolonged another three years. However, the
subcontract between Ansaldo and Serco Group was not extended, and
the contract was instead given to
Azienda Trasporti Milanese in
joint venture with Ansaldo, who took over operations from October
2007. In 2007, the Ørestad Development Corporation was
discontinued, and the ownership of the metro was transferred to
Metroselskabet I/S.
In
January 2007, the city council decided that a branch be built
during construction at Norreport, to allow a future branch line
from the City Circle Line towards Brønshøj
. The start of must be built at the same time
of the City Circle Line being built, or face a multitude higher
construction costs and long stop of operations later. The decision
did not actually involve a final decision to built the metro
branch. In March 2007, a proposal to establish a station at
Valby, where
Carlsberg is planning an urban redevelopment, was
scrapped. This would increase construction costs with DKK 900
million, and was not economic. The high costs were in part due to
an extra TBM being needed to finished the project in time. The City
Circle Line was passed by parliament on 1 June 2007, with only the
Red–Green Alliance
voting in disfavor.
The stage 3 opened on 28 September 2007, from Lergravsparken to the
airport.
It followed for the most part the route of
the former Amager Line of the Danish State
Railways
. With this stage complete, 34 trains had
been delivered. However, the line had caused a heated debate, and
several locals had organized themselves in the Amager Metro Group.
They demanded that the line instead be tunneled, arguing that it
caused a physical barrier in Amager and that it created noise
pollution. In April 2008, the Copenhagen Metro won the award at
MetroRail 2008 for the world's best metro. The jury noted the
system's high regularity, safety and passenger satisfaction, as
well as the efficient transport to the airport. During 2008, the
metro experienced a 16% passenger growth to 44 million passengers
per year.
An agreement made in September 2008, the
Social Democrats, the
Conservative People's
Party , the
Liberal
Party and the
Danish People's
Party agreed to not fund an expansion of the metro northwest.
Initially, the system had night trains on Thursday, Friday and
Saturday night, but from 19 March 2009, this was extended to all
nights. This caused a logistical challenge, because the operator
used the nights for maintenance. The routes were therefore set up
in such a way that the system could be operated on only a single
track, leaving the other free for work. In May 2009, six companies
were pre-qualified to bid for the
public service obligation to
operate the metro.
These were Serco–NedRailways, Ansaldo STS, Arriva, S-Bahn Hamburg,
Keolis and DSB Metro—a joint venture between
DSB
and RATP. The process
was delayed because of a procedural error by Metroselskabet, who
failed to prequalify DSB Metro.
Route

A map of the Copenhagen Metro
network
The metro consists of two lines, M1 and M2.
They share a common
section from Vanløse to Christianshavn
, where they split along two lines, M1 along the
Ørestad Line to Vestamager, and M2 the Østamager Line to the
airport. The lines have 22 stations and are long, of which 9
stations and km are on the common section. M1 is long and has 15
stations, while M2 is long and has 16 stations. About of the lines
and nine stations are in tunnel, located at below ground level. The
remaining are on embankments, viaducts or at ground level.
The section from Vanløse to Frederiksberg follows the Frederiksberg
Line, a former S-train line that runs on an embankment, and is
located in Frederiksberg Municipality. Between Solbjerg and
Frederiksberg, the line runs underground, and continues through the
city center. After Christianshavn, the line splits in two. M1
reaches ground level at Islands Brygge, and continues on a viaduct
until the Vestamager area. M2 continues in tunnel until after
Lergravsparken, where it starts to follow the former Amager
Line.
The tunnels consists of two parallel barrels; the run through
stable
limestone at about depth, but are
elevated slightly at stations. There are emergency exits every , so
the train is at any time not further than away from one. The outer
tunnel diameter is , while the inner diameter is . The tunnels have
been excavated using
boring with
tunnel boring machines (TBM),
cut-and-cover and
new Austrian tunnelling
method. On the elevated sections, the tracks lay on each their
parallel pylon-supported viaducts.
Service
The system operates continually with a varying
headway throughout the day. During rush hour (07–10
and 15–18), there is a two-minute headway on the common section and
a four-minute headway on the individual sections. During Thursday
through Saturday night (24–05), the headway is fifteen minutes, and
other night it is twenty minutes on all sections of the metro. At
all other times, there is a three-minute headway on the common
section and a six-minute on the split sections. Travel time from
Nørreport to Vestamager on M1 is 14 minutes, to the airport on M2
is 15 minutes, and to Vanløse on M1 and M2 is 9 minutes. In 2008,
the metro transported 47 million passengers, or 149,000 per
day.
The metro operates with a
proof-of-payment system, so riders must
have a valid ticket before entering the station platforms. The
system is divided into
zones, and the fare
structure is integrated into other public transport in Copenhagen,
including the buses managed by Movia, local DSB trains and the
S-train. The system lays within four different zones.
Ticket machines are available at all
stations, where special tickets for dogs and bicycles can be
purchased. A two-zone ticket costs DKK 21, with discounts
available for multi-ride tickets. Tickets must be stamped to be
validated. Holders of the Copenhagen Card ride free of charge, as
do up to two children under twelve years of age accompanied by an
adult. In 2010, the metro will adapt the national electronic fare
card system
Rejsekort.
The system is integrated with other public transport in Copenhagen.
There is
transfer to to the S-train at Vanløse, Flintholm
and Nørreport, to DSB's local trains at Nørreport,
Ørestad
and Lufthavnen, and to Copenhagen Airport at
Lufthavnen. There are transfers to Movia bus services at all
but four stations.
The system is owned by Metroselskabet, who is also responsible for
building the City Circle Line. The company is owned by Copenhagen
Municipality (50.0%), the Ministry of Transport (41.7%) and
Frederiksberg Municipality (8.3%). The company is organized with as
few employees as possible. Construction and operation is
subcontracted through public tenders, while consultants are used
for planning. The contract to operate the system was made with
Ansaldo STS, who has subcontracted it to Metro Service, a joint
venture between them and Aziende Trasporti Milanese. The company
has about 200 employees, the majority who work as stewards.
Stations
There are 22
stations on the network,
of which nine are underground and six are deep-level. The stations
were designed by
KHR Arkitekter, and
are designed to create openness and daylight to clarify the depth
of the stations. They have a information column in front of the
station, marked with a large 'M' and with information screens. All
stations have a
vestibule
at ground level, that has ticket and local information, ticket
machines and validators. The stations are built with
island platforms. The stations are fully
accessible for people with
disabilities.
The six deep-level stations are built as square, open boxes long,
wide and long. The platforms are located below the surface. Access
to the surface is reached via escalators and elevators. The design
allows the stations to located below streets and squares, and means
no
expropriation is needed. Access to
the track is blocked by
platform
screen doors. The underground stations were built as
cut-and-cover from the top down, and the first part of construction
was building a water-tight wall on all sides. There are glass
pyramids on the roof of the stations permitting daylight to enter.
Inside the pyramids, there are
prism
refracting and splitting the light, sometimes resulting in rainbows
on the walls. The light on the stations is automatically regulated
to make best use of the daylight and maintain a constant level of
illumination of the stations at all times.
The elevated stations are built in glass, concrete and steel, to
minimize their visual impact. Outside, there is parking for
bicycles, cars, buses and taxis. The platforms are open, but have
sheds, and automatic sensors that halt trains if obstacles are
detected on the tracks.
Trains
The interior of a Metro train
The system uses 34 driverless
electric multiple units built by
AnsaldoBreda and designed by Giugiaro
Design of Italy.The trains are long, wide, and weigh . Each train
consists of three articulated cars with a total of six automated,
wide doors, holding up to 96 seated and 204 standing passengers.
There are four large 'flex areas' in each train with folding seats
providing space for wheelchairs, strollers and bicycles.
Each car is equipped with two
three-phase asynchronous motors, giving each train a power output of .
In each car, the two motors are fed by the car's own
insulated-gate bipolar
transistor. They transform the 750 volt direct current
collected from the
third rail shoe to the
three-phase alternating current used in the motors. The trains' top
speed are , while the average service speed is , with an
acceleration and deceleration capacity of 1.3 m/s
2
(4.3 ft/s
2). The track is
standard gauge.
The entire metro system and the trains are run by a fully-automated
computer system, located at the Control and Maintenance Center
south of Vestamanger Station. The
automatic train control (ATC)
consists of three subsystems:
automatic train protection (ATP),
automatic train operation
(ATO) and
automatic train
supervisory (ATS). The ATP is responsible for keeping the
trains' speed, insuring that doors are closed before departure and
insuring that
switches are correct
set. The system uses
fixed block
signaling, except around stations, where moving block signaling
is used.

The control room
The ATO is the
autopilot that drives the
trains after a predefined schedule, insures that the train stop at
stations and operates the doors. The ATS keeps track of all
components of the network, including the rails and all trains on
the system, and displays a live schematic at the control center.
The ATC is designed to that only the ATP is safety-critical, and
will halt trains if the other systems have faults.
The safety and
signaling specifications are based on the German BOStrab, and controlled by TÜV
Rheinland
and Det Norske Veritas
under authority of the Public Transport
Authority.Other aspects of the system, such a power supply,
ventilation, security alarms, cameras and pumps, are controlled by
a system called "control, regulating and
surveillance".
The Control and Maintenance Center is an facility located at the
south of M1. It consist of both a storage area for trains not in
use, a maintenance area and the control facility for the whole
system. The trains operate automatically through the system, and
can also automatically be washed on the exterior. The facility has
of track, of which is a test track for use after maintenance. The
most common repairs are the grinding of the wheels; more
complicated repairs are made by replacing entire components that
are sent to the manufacturer. By having components in reserve,
trains can have shorter maintenance time. The center also has the
system's work trains, that include a diesel locomotive that can
fetch broken trains.
At any time, there are four people working at the control center.
Two monitor the ATC system, one monitors passenger information,
while the last is responsible for secondary systems, such as power
supply. In case of technical problems, there is always a team of
linemen that can be sent to perform repairs. Although the trains
are not equipped with drivers, there are stewards that help
passengers, perform ticket controls and assist in emergency
situations.
Future
Diagram of the Copenhagen Metro including the proposed lines M3 and
M4.
Station names shown in brackets are provisional and may change
before M3/M4 is completed.
The City Circle Line is an under-construction expansion of the
metro.
Independent of the existing system, it will
circle the city center and connect the areas of Østerbro
, Nørrebro and Vesterbro to Frederiksberg and Indre By
. The line will be long and run entirely in
tunnel. The circle will have 17 stations, and it will take 25
minutes to complete a full circle. Archaeological and geological
surveys started in 2007, and construction of the tunnels is planned
to start in 2010.
The line
will operate as M3 and M4, the former taking a full circle, while
M4 will only operate on the eastern half from Copenhagen
Central Station
via Østerport
to Nørrebro
. Trains will operate both ways through the
circle.
The line will have transfer to M1 and M2 at
Frederiksberg and Kongens Nytorv
. The line is estimated to carry 240,000
daily passengers, bringing the metro's total daily ridership to
460,000.
A further
expansion of the City Circle Line has been proposed, where M4 would
divert at Nørrebro and run to the suburbs of Brønshøj
and Gladsaxe
. There are two proposals, one that will have
four stations and run to Husum
, and one
that will have nine stations and run to Gladsaxe. The
authorities are also considering light rail and
bus rapid transit. The long metro model
would be long, give a 400% increase in public transport ridership
in the area, and cost DKK 9.3 billion to build.
References
External links