The
economics of new nuclear power plants is a
controversial subject, since multi-billion dollar investments ride
on the choice of an energy source.
Nuclear power plants typically have high
capital costs for building the plant, but low fuel costs.
Therefore, comparison with other power generation methods is
strongly dependent on assumptions about construction timescales and
capital financing for nuclear plants. Cost estimates also need to
take into account
plant
decommissioning and
nuclear waste
storage costs. On the other hand measures to
mitigate global warming, such as a
carbon tax or
carbon emissions trading, may favor
the economics of nuclear power.
Analysis of the economics of nuclear power must take into account
who bears the risks of future uncertainties. To date all operating
nuclear power plants were developed by
state-owned or
regulated utility monopolies where many of the risks
associated with construction costs, operating performance, fuel
price, and other factors were borne by consumers rather than
suppliers. Many countries have now liberalized the
electricity market where these risks, and
the risk of cheaper competitors, are borne by plant suppliers and
operators rather than consumers, which leads to a significantly
different evaluation of the economics of new nuclear power
plants.
Capital costs
Because of the large capital costs for nuclear power, and the
relatively long construction period before revenue is returned,
servicing the capital costs of a
nuclear power plant is the most important factor determining the
economic competitiveness of nuclear energy. The investment can
contribute about 70% of costs of electricity, according to one 2005
OECD/NEA study (which assumed a 10%
discount rate). The
discount rate chosen to cost a nuclear power
plant's capital over its lifetime is arguably the most sensitive
parameter to overall costs.
The recent liberalization of the
electricity market in many countries has
made the economics of nuclear power generation less attractive.
Previously a monopolistic provider could guarantee output
requirements decades into the future. Private generating companies
now have to accept shorter output contracts and the risks of future
lower-cost competition, so they desire a shorter return on
investment period — this favours generation plant types with lower
capital costs even if associated fuel costs are higher. A further
difficulty is that due to the large sunk costs but unpredictable
future income from the liberalised electricity market, private
capital is unlikely to be available on favourable terms, which is
particularly significant for nuclear as it is capital-intensive.
Industry consensus is that a 5% discount rate is appropriate for
plants operating in a regulated utility environment where revenues
are guaranteed by captive markets, and 10% discount rate is
appropriate for a competitive deregulated or merchant plant
environment, however the independent MIT study (2003) which used a
more sophisticated finance model distinguishing equity and debt
capital had a higher 11.5% average discount rate.
However, another consideration is that even though consumer demand
is not guaranteed, nuclear is placed among the lowest operating
cost options. Once the plant is built, it has a distinct advantage
over coal, gas, and other fuel based generation types in winning
the momentary supply auctions, thereby resulting in operations at
full reactor capacity. In this regard, typical Present Value (PV)
calculations for risk-adjusted discount should be applied
carefully, possibly approaching the guaranteed, captive market
levels.
The smallest nuclear power plant that can be built is often larger
than other power plants, making it possible for a utility to build
the other plants in smaller increments, or in areas of low power
consumption. (However, several new designs are being targeted at
smaller markets, such as
PBMR,
IRIS, and
SSTAR).
Recent construction cost estimates
2007 estimates have considerable uncertainty in
overnight cost, and vary widely from
$2,950/kWe (
overnight cost) to a
Moody's Investors Service
conservative estimate of between $5,000 and $6,000/kWe (final or
"all-in" cost).
However, commodity prices shot up in 2008, and so all types of
plants will be more expensive than previously calculated In June
2008 Moody's estimated that the cost of installing new nuclear
capacity in the U.S. might possibly exceed $7,000/kWe in final
cost.
The reported prices at six new
pressurized water reactors are
indicative of costs for that type of plant:
- February 2008 — For two new AP1000
reactors at its Turkey Point site Florida Power & Light
calculated overnight capital cost from $2444 to $3582 per kW, which
were grossed up to include cooling towers, site works, land costs,
transmission costs and risk management for total costs of $3108 to
$4540 per kilowatt. Adding in finance charges increased the overall
figures to $5780 to $8071 per kW.
- March 2008 — For two new AP1000 reactors in Florida Progress
Energy announced that if built within 18 months of each other, the
cost for the first would be $5144 per kilowatt and the second
$3376/kW - total $9.4 billion. Including land, plant components,
cooling towers, financing costs, license application, regulatory
fees, initial fuel for two units, owner's costs, insurance and
taxes, escalation and contingencies the total would be about $14
billion.
- May
2008 — For two new AP1000 reactors at the Virgil C.
Summer Nuclear Generating
Station
in South Carolina South Carolina Electric and Gas
Co. and Santee Cooper expected to pay $9.8 billion (which includes
forecast inflation and owners' costs for site preparation,
contingencies and project financing).
- November 2008 — For two new AP1000 reactors at its Lee site
Duke Energy Carolinas raised the cost estimate to $11 billion,
excluding finance and inflation, but apparently including other
owners costs.
- November 2008 — For two new AP1000 reactors at its Bellefonte
site TVA updated its estimates for overnight capital cost estimates
ranged to $2516 to $4649/kW for a combined construction cost of
$5.6 to 10.4 billion (total costs of $9.9 to $17.5 billion).
- On
April 9, 2008, Georgia Power Company reached a
contract agreement for two AP1000 reactors to be built at Vogtle
, at an estimated final cost of $14 billion
plus $3 billion for necessary transmission
upgrades.
Effect of delays
Construction delays can add significantly to the cost of a plant.
Because a power plant does not yield profits during construction,
longer construction times translate directly into higher finance
charges. Modern nuclear power plants are planned for construction
in four years or less (42 months for CANDU ACR-1000, 60 months from
order to operation for an
AP1000, 48 months
from first concrete to operation for an
EPR and 45 months for an
ESBWR) as opposed to over a decade for some
previous plants.
However, despite Japanese success with
ABWRs, the first EPR (in Finland
) is
significantly behind schedule.
In some countries (notably the U.S.), in the past unexpected
changes in licensing, inspection and certification of nuclear power
plants added delays and increased construction costs in the past.
However, the regulatory processes for siting, licensing, and
constructing have been standardized, streamlining the construction
of newer and safer designs.
In the
U.S. many new regulations were put in place in the years before and
again immediately after the Three Mile Island accident
's partial meltdown, resulting in plant startup
delays of many years. The NRC has new regulations in place
now (see
Combined
Construction and Operating License), and the next plants will
have NRC Final Design Approval before the customer buys them, and a
Combined Construction and Operating License will be issued before
construction starts, guaranteeing that if the plant is built as
designed then it will be allowed to operate — thus avoiding lengthy
hearings after completion.
In
Japan
and France
,
construction costs and delays are significantly diminished because
of streamlined government licensing and certification
procedures. In France, one model of reactor was
type-certified, using a
safety
engineering process similar to the process used to certify
aircraft models for safety. That is, rather than licensing
individual reactors, the regulatory agency certified a particular
design and its construction process to produce safe reactors. U.S.
law permits type-licensing of reactors, a process which is being
used on the
AP1000 and the
ESBWR.
To encourage development of nuclear power, under the
Nuclear Power 2010 Program the
U.S. Department of Energy
(DOE) has offered interested parties the opportunity to introduce
France's model for licensing and to subsidize 25% to 50% of the
construction cost overruns due to delays for the first six new
plants. Several applications have been made, two sites have been
chosen to receive new plants, and other projects are pending (see
Nuclear Power 2010
Program).
Operating costs
In general, coal and nuclear plants have the same types of
operating costs (operations and maintenance plus fuel costs).
However, nuclear has lower fuel costs but higher operating and
maintenance costs.
Security
Unlike other power plants, nuclear plants must be carefully guarded
against both attempted sabotage (generally with the goal considered
to be causing a radiological accident, rather than just preventing
the plant from operating) and possible theft of nuclear material.
Thus security costs of both protecting the physical plant and the
screening of workers must be considered. Some other forms of energy
also require high security, like natural gas storage facilities and
oil refineries.
Uranium
Nuclear plants require
fissionable
fuel. Generally, the fuel used is
uranium,
although other materials may be used (
See MOX fuel). In 2005, prices on the world market
averaged
US$20/lb (US$44.09/kg). On 2007-04-19,
prices reached US$113/lb (US$249.12/kg). On 2008-7-2, the price had
dropped to $59/lb.
While the amounts of uranium used are a fraction of the amounts of
coal or oil used in conventional power plants, fuel costs account
for about 28% of a nuclear plant's operating expenses. Other recent
sources cite lower fuel costs, such as 16%. Doubling the price of
uranium would add only 7% to the cost of electricity
produced.
Currently, there are proposals to increase the numbers of nuclear
power plants by 57% more reactors from the 435 currently in
operation, according to John S. Herold's Ruppel. While it is
unlikely all proposed plants will actually be completed, an
increase in plants, combined with the current decline in supply,
caused by flooding at some of the world's largest uranium mines,
and speculators winning repositories in North America and Europe,
means that prices are likely to increase. In addition, about 45% of
the 2006 world supply of uranium came from old nuclear warheads,
mostly Russian. At current supply and demand levels, those old
stockpiles will be completely depleted by 2015.
Mining activity is growing rapidly, especially from smaller
companies, but developing a uranium mine takes a long time, 10
years or more.
The world's present measured resources of
uranium, economically recoverable at a price of 130 USD/kg
according to the industry groups Organisation
for Economic Co-operation and Development (OECD), Nuclear Energy Agency (NEA) and
International Atomic Energy
Agency
(IAEA), are enough to last for "at least a century"
at current consumption rates.
Waste disposal
All nuclear plants produce radioactive waste. Medium and high level
wastes are strong emitters of radiation and will require shielding
for thousands of years. The status of waste disposal plans in
various countries are described in other articles, notably
radioactive waste and
high-level radioactive
waste management.
To pay for the cost of storing, transporting and disposing these
wastes in a permanent location, in the United States a surcharge of
a tenth of a
cent per
kilowatt-hour is added to electricity bills.
In 2009,
the Obama administration announced that
the Yucca Mountain nuclear waste
repository
would no longer be considered the answer for U.S.
civilian nuclear waste. Currently, there is no plan for
disposing of the waste and plants will be required to keep the
waste on the plant premises indefinitely.
The disposal of
low level waste
reportedly costs around £2,000/m³ in the UK.
High level waste costs somewhere between
£67,000/m³ and £201,000/m³. General division is 80%/20% of low
level/high level waste, and one reactor produces roughly 12 m³ of
high level waste annually.
Decommissioning
At the end of a nuclear plant's lifetime (estimated at between 40
and 60 years), the plant must be decommissioned. This entails
either Dismantling, Safe Storage or Entombment. Operators are
usually required to build up a fund to cover these costs while the
plant is operating, to limit the financial risk from operator
bankruptcy.
In the United States, the
Nuclear Regulatory Commission
(NRC) requires plants to finish the process within 60 years of
closing. Since it may cost $300 million or more to shut down
and decommission a plant, the NRC requires plant owners to set
aside money when the plant is still operating to pay for the future
shutdown costs. In June 2009, the NRC published concerns that
owners were not setting aside sufficient funds.
Insurance
US
Insurance
for nuclear or radiological incidents in the U.S.
is organized
by the Price-Anderson
Nuclear Industries Indemnity Act. In general, nuclear
power plants have private insurance and assessments that are pooled
into a fund currently worth about $10 billion. Insurance claims
beyond the fund's size would be organized by, and probably paid by,
the U.S. government. In July 2005,
Congress extended this Act to
newer facilities. For full history, details and controversy, see
Price-Anderson
Nuclear Industries Indemnity Act.
UK
In the
UK
, the
Nuclear Installations Act
of 1965 governs liability for nuclear damage for which a UK nuclear
licensee is responsible. The limit for the operator is
£140 million.
Other
The
Vienna
Convention on Civil Liability for Nuclear Damage and the
Paris Convention on Third Party Liability in the Field of Nuclear
Energy put in place two similar international frameworks for
nuclear liability.. The limits for the conventions vary. The Vienna
convention was adapted in 2004 to increase the operator liability
to €700 million per incident, but this modification is not yet
ratified.
The nuclear industry states that it already has a large liability
insurance, and that it would be unfair to demand full liability for
its plants, the insurance industry cannot to supply full liability
insurance, and environmental NGOs demand that the polluter pays
principle is applied to this aspect of the nuclear industry, and
state that for every € 8.000 of third party damages after a nuclear
accident, only € 1 of private insurance could be available .
Load following capability
Most existing plants (excepting
BWR and
CANDU types) have limited ability to significantly
vary their output to match changing demand (called
load-following). As such, nuclear
power reactors are generally intended solely for
baseload supply.
This means they would be unlikely to provide 100% of the generation
on most large grids. Also many techniques such as demand
management, smart grids, interconnections are required in the same
way that they will be for most intermittent renewable such as wind.
It is considered by
E.On of Germany and
EDF Energy of the UK that nuclear and
renewable are incompatible for this reason.
Some newer reactors offer some form of enhanced load-following
capability.
Cost per kW·h
The cost per unit of electricity produced (kW·h) will vary
according to country, depending on costs in the area, the
regulatory regime and consequent financial and other risks, and the
availability and cost of finance. Costs will also depend on
geographic factors such as availability of cooling water,
earthquake likelihood, and availability of suitable power grid
connections. So it is not possible to accurately estimate costs on
a global basis.
Various groups have attempted to estimate the economic cost for
electricity generated by the most modern designs proposed for
particular countries where these factors are generally fairly
consistent.
In 2003,
the Massachusetts Institute of
Technology
(MIT) issued a report entitled, "The Future of
Nuclear Power". They estimated that new nuclear power in the
US would cost 6.7 cents per kW·h. However, the
Energy Policy Act of 2005 includes
a tax credit that should reduce that cost slightly.
The lifetime cost of new generating capacity in the United States
was estimated in 2006 by the U.S. government (the 2007 report did
not estimate costs). Nuclear power was estimated at 5.93 cents
per kW·h. However, the "total overnight cost" for new nuclear was
assumed to be $1,984 per kWe — as seen above in Capital Costs, this
figure is subject to debate.
A 2008 study based on historical outcomes in the U.S. said costs
for nuclear power can be expected to run $0.25-.30 per kW·h.
A 2008 study concluded that if carbon capture and storage was
required then nuclear power would be the cheapest source of
electricity even at $4,038/kW in overnight capital cost.
In 2009, MIT updated its 2003 study, concluding that inflation and
rising construction costs had increased the overnight cost of
nuclear power plants to about $4,000/kWe, and thus increased the
power cost to 8.4¢/kW·h.
Comparisons with other power sources
See Also:
Relative
cost of electricity generated by different sources
Generally, a nuclear power plant is significantly more expensive to
build than an equivalent coal-fueled or gas-fueled plant. However,
coal is significantly more expensive than nuclear fuel, and natural
gas significantly more expensive than coal — thus, capital costs
aside, natural gas-generated power is the most expensive. Most
forms of electricity generation produce some form of
negative externality — costs imposed on third
parties that are not directly paid by the producer — such as
pollution which negatively affects the
health of those near and downwind of the power plant, and
generation costs often do not reflect these external costs.
A comparison of the "real" cost of various energy sources is
complicated by several uncertainties:
- The cost of climate change through emissions of greenhouse gases is hard to estimate.
Carbon taxes may be enacted, or carbon capture and storage may
become mandatory.
- The cost of environmental damage caused by (fossil or
renewable) energy sources, both through land use (whether for
mining fuels or for power generation) and through air and water
pollution and solid waste.
- Outside the U.S., the cost or political feasibility of disposal
of the waste from reprocessed
spent nuclear fuel is still not
fully resolved. Disposal of U.S. spent nuclear fuel, which
currently is not reprocessed, is funded by a fixed surcharge on
generation which funds the U.S. government taking possession of and
title to the fuel.
- Operating reserve requirements
are different for different generation methods. When nuclear units
shut down unexpectedly they tend to do so independently, so the
"hot spinning reserve" must be at least the size of the largest
unit (this partly makes nuclear power more suitable for large
grids). On the other hand, many renewables are intermittent power sources and may
shut down together if they depend on weather conditions, so the
grid will require either back-up generation capability or
large-scale storage if the portion of generation from these
renewables is significant. (Some renewables such as hydroelectricity have a storage reservoir
and can be used as reliable back-up power for other power
sources.)
- Governmental instabilities in the next plant lifetime. New
nuclear power plants are designed for a minimum of 60 years
(50 for VVER-1200), and may be able to be refurbished. Likewise,
the waste from reprocessed fuel remains dangerous for about this
period.
- Actual plant lifetime (to date, no plant has been shut down due
to maximum licensed lifetime being reached, or been
refurbished).
- Due to the dominant role of initial construction cost and the
multi-year construction time and planned lifetime, the interest
rate for the capital required is of particularly high importance
for estimating the total cost.
Several recent comparisons of the costs of plants are available
(see below); however, commodity prices have shot up since they were
completed, and so all types of plants will be more expensive than
shown
A UK Royal Academy of Engineering report in 2004 looked at
electricity generation costs from new plants in the UK. In
particular it aimed to develop "a robust approach to compare
directly the costs of intermittent generation with more dependable
sources of generation". This meant adding the cost of standby
capacity for wind, as well as carbon values up to £30 (€45.44) per
tonne CO
2 for coal and gas. Wind power was calculated to
be more than twice as expensive as nuclear power. Without a carbon
tax, the cost of production through coal, nuclear and gas ranged
£0.022–0.026/
kW·h and coal gasification
was £0.032/kW·h. When carbon tax was added (up to £0.025) coal came
close to onshore wind (including back-up power) at £0.054/kW·h —
offshore wind is £0.072/kW·h — nuclear power remained at
£0.023/kW·h either way, as it produces negligible amounts of
CO
2. (Nuclear figures included estimated decommissioning
costs.)
However a much more detailed review of over 200 papers by the UK
Energy Research Centre, on the issue of intermittency came to much
lower costs about the cost of wind energy compared to nuclear
energy. A recent study shows the current generating costs of wind,
nuclear and coal plant in the UK which stills shows nuclear the
cheapest, but not by a great a margin.
The lifetime cost of new generating capacity in the United States
was estimated in 2006 by the U.S. government: wind cost was
estimated at $55.80 per MW·h, coal (cheap in the U.S.) at $53.10,
natural gas at $52.50 and nuclear at $59.30. However, the "total
overnight cost" for new nuclear was assumed to be $1,984 per kWe —
as seen above in Capital Costs, this figure is subject to debate,
as much higher cost was found for recent projects. Also, carbon
taxes and backup power costs were not considered.
A May 2008 study by the
Congressional Budget Office
concludes that a carbon tax of $45 per metric ton would probably
make nuclear power cost competitive against conventional fossil
fuel for electricity generation.
Costs for
Clean coal and
Carbon capture and storage can be
found in those articles.
Estimates of total lifetime energy returned on energy invested vary
greatly depending on the study. An overview can be found here
(Table 2):
The effect of subsidies is difficult to gauge, as some are indirect
(such as research and development). A May 12, 2008 editorial
in the
Wall Street
Journal stated, "For electricity generation, the
EIA(Energy Information Administration, an office of the Department
of Energy) concludes that solar energy is subsidized to the tune of
$24.34 per megawatt hour, wind $23.37 and 'clean coal' $29.81. By
contrast, normal coal receives 44 cents, natural gas a mere
quarter, hydroelectric about 67 cents and nuclear power
$1.59."
Other economic issues
Nuclear Power plants tend to be very competitive in areas where
other fuel resources are not readily available — France, most
notably, has almost no native supplies of fossil fuels.
Making a massive investment of capital in a project with long-term
recovery might impact a company's credit rating.
Any effort to construct a new nuclear facility around the world,
whether an existing design or an experimental future design, must
deal with
NIMBY or NIABY objections.
Because
of the high profiles of the Three Mile Island accident
and Chernobyl disaster
, relatively few municipalities welcome a new
nuclear reactor, processing plant, transportation route, or nuclear
burial ground within their borders, and some have issued local
ordinances prohibiting the locating of such facilities
there. However, a number of U.S. areas, some already with
nuclear units, are campaigning for more (see
Nuclear Power 2010
Program).
A
Council on Foreign
Relations report on nuclear energy argues that a rapid
expansion of nuclear power may create shortages in building
materials such as reactor-quality concrete and steel, skilled
workers and engineers, and safety controls by skilled inspectors.
This would drive up current prices. It may be easier to rapidly
expand, for example, the number of coal power plants, without this
having a large effect on current prices.
The number of companies that manufacture certain parts for nuclear
reactors is limited, particularly the large forgings used for
reactor vessels and steam systems.
Only four companies (Japan Steel Works, China First Heavy Industries,
Russia's OMX Izhora and Korea's Doosan Heavy Industries
) currently manufacture pressure vessels for
reactors of 1100 MWe or larger. Some have suggested that
this poses a bottleneck that could hamper expansion of nuclear
power internationally, however, some Western reactor designs
require no steel pressure vessel such as
CANDU
derived reactors which rely on individual pressurized fuel
channels. The large forgings for steam generators — although still
very heavy — can be produced by a far larger number of
suppliers.
Nuclear plants require 20–83 percent more cooling water than other
power stations. During times of abnormally high seasonal
temperatures or drought it may be necessary for reactors drawing
from small bodies of water to reduce power or shut down. Nuclear
plants situated on large lakes, seas or oceans are not affected by
seasonal temperature variations due to the thermal stability of
large bodies of water.
New plants under construction
The latest plant designs currently available for building are
generally called
generation III+
reactors. They include
AREVA's
European Pressurized Reactor
(EPR), General Electric's
ESBWR,
Westinghouse's
AP1000, and AECL's
ACR-1000. Russia (see
VVER), Japan, Korea, India and China all also have
indigenous plant designs currently available for deployment.
In 2008 China ordered 100 reactors from Westinghouse Nuclear, all
to be operational or under construction by 2020, in addition to
other reactors planned or under construction (see
Nuclear power in China).
According to the
NRC,
as of August, 2008 35 new U.S. nuclear power units are planning to
apply for licenses. Early Site Permit Applications have been filed
in the U.S. for several
AP1000 plants.
In July 2008, Russia announced plans to allocate $40 billion from
the state budget over the next 7 years for development of the
nuclear energy sector and the nuclear industry. This will allow for
construction of 26 major generating units in Russia by 2020 — about
as many as were built in the entire Soviet period.
As of 2008, the UK has indicated that it will take steps to
encourage private operators to build new nuclear power plants in
the coming years to meet projected energy needs as
fossil fuel prices climb, however there would be
no subsidies from the UK government for nuclear power. An online
calculator outlining UK means and limitations in meeting future
energy needs illustrates the problem facing lawmakers and the
public.
The 1600
MWe European Pressurized Reactor
(EPR) reactor is being built in Olkiluoto
Nuclear Power Plant
, Finland
. A
joint effort of French
AREVA and German
Siemens AG, it will be the largest
PWR in the world. The
Olkiluoto project has benefited from various forms of government
support and subsidies, including liability limitations,
preferential financing rates, and export credit agency subsidies.
However, as of August 2009, the project is "more than three years
behind schedule and at least 55% over budget, reaching a total cost
estimate of €5 billion ($7 billion) or close to €3,100 ($4,400) per
kilowatt".
Four
ABWRs are already in operation in Japan
, and one
more is being built in Japan and two in Taiwan
. Two
of the Japanese plants were brought in under budget and ahead of
schedule.
Several Indian plants are planned as of 2008.
Russia
has begun
building the world’s first floating nuclear power
plant. The £100 million vessel, the
Akademik
Lomonosov, is the first of seven plants (70 MWe per ship)
that Moscow says will bring vital energy resources to remote
Russian regions.
SSTAR, a leased reactor intended for
developing nations, is under development.
South Korea
plans to build 12 new nuclear power plants from
2009 to 2022.
See also
External links
- The Economics of Nuclear Power, World Nuclear Association, May
2008
- "The Economics of Nuclear Power: analysis of recent
studies", Steve Thomas, PSIRU, University
of Greenwich
, July 2005
- The Political Economy of Nuclear Energy in the
United States, Brookings Institution, September 2004
- Advanced Nuclear Power Reactors, World Nuclear
Association, May 2008
- The Future will not be Nuclear article by
Tom Burke,
Environmental Policy Advisor for Rio
Tinto, 2008.
- The Nuclear Illusion report by Amory Lovins, Chief Scientist, Rocky
Mountain Institute
, 2008.
References
- >
-
http://www.world-nuclear-news.org/C-STP_sets_new_US_operating_record-0710084.html
- http://www.nei.org/newsandevents/recordlowcosts/
- Nuclear Costs Explode.
- Platts: A utility's credit quality could be negatively
impacted by building a new nuclear power plant, 2 June 2008,
Moody's Investors Service
- What's behind the red-hot uranium boom, 2007-04-19,
CNNMoney,
Retrieved 2008-07-2
- Safe Transportation of Spent Nuclear Fuel,
January 2003, The Center for Reactor Information, Retrieved 1 June
2007
- Nuclear Engineering International
- Nuclear Energy Data 2008, OECD, p. 48 (the Netherlands, Borssele nuclear power
plant)
- Decommissioning a Nuclear Power Plant,
2007-4-20, U.S.
Nuclear Regulatory Commission, Retrieved 2007-6-12
- [1]
- Civil Liability for Nuclear Damage: WNA
- Vienna Convention on Civil Liability for Nuclear
Damage, IAEA, 12/11/1977
- Press Communiqué 6 June 2003 - Revised Nuclear Third Party
Liability Conventions Improve Victims' Rights to
Compensation
- http://www.world-nuclear.org/info/inf67.html
- Swiss RE: http://www.swissre.com/resources/bf6bda00455c563e96e7be80a45d76a0-NuclearRisk.pdf
- Friends of the Earth — Nuclear industry: Face your demons - towards full
liability for nuclear power plant operators
-
http://www.claverton-energy.com/nuclear-power-stations-cant-load-follow-that-much-official.html
-
http://www.claverton-energy.com/nuclear-and-wind-are-officially-stated-to-be-incomptible.html
-
http://www.cessa.eu.com/sd_papers/wp/wp2/0203_Pouret_Nuttall.pdf
- Assumptions to the Annual Energy Outlook 2006 - see
p.73
- Severance, C. (2009) "Business Risks and Costs of New Nuclear
Power"; for critiques and replies from the study's author, see
http://climateprogress.org/2009/01/05/study-cost-risks-new-nuclear-power-plants/
-
http://www.ukerc.ac.uk/ResearchProgrammes/TechnologyandPolicyAssessment/TPAProjectIntermittency.aspx
UK Energy Research Council Report on effects of intermittent wind
energy
- http://www.claverton-energy.com/?dl_id=314
- http://www.eia.doe.gov/oiaf/ieo/pdf/0484(2006).pdf Energy
Information Administration, "International Energy Outlook", 2006,
p. 66.
- Wind ($23.37) v. Gas (25 Cents), Wall
Street Journal, May 12, 2008
- [2]
- [3]
- Nuclear power and water scarcity, ScienceAlert,
28 October 2007, Retrieved 2008-08-08
- $40 Billion boost for nuclear power in Russia
Russia Today
Retrieved on July 31, 2008
- BBC's UK Electricity Calculator illustrates new nuclear role to
meet future demand.
http://news.bbc.co.uk/2/shared/spl/hi/uk/06/electricity_calc/html/1.stm
-
http://www.energyprobe.org/energyprobe/images/NuclearCost/NuclearCost_files/frame.htm
Energy Probe, "Critique of the Official View of Ontario's Energy
Future", Presentation to the Canadian Academy of Engineering, June
2007.
- Mycle
Schneider, Steve Thomas, Antony Froggatt,
Doug Koplow (August 2009). The World Nuclear Industry Status Report 2009
Commissioned by German Federal Ministry of Environment, Nature
Conservation and Reactor Safety, p. 7.
- Advanced Boiling Water Fact Sheet GE
Hitachi]
- BBC NEWS | Europe | Nuclear power around the
world
- Floating nuclear power stations raise spectre of
Chernobyl at sea
- South Korea to build 12 new nuclear power
plants