
Paris Metro.
The guiding rails of the rubber-tyred lines are also current
conductors.
The current collector is between the pair of rubber
wheels.

London Stansted Airport people mover
central rail.

London Stansted Airport people mover,
showing rail switch.
A
third rail is a method of providing
electric power to a
railway train, through a continuous rigid
conductor placed alongside or between the rails of a railway track.
It is used typically in a
mass transit
or
rapid transit system, which has
alignments in its own corridors, fully or almost fully segregated
from the outside environment. In most cases, third rail systems
supply
direct current
electricity.
The third-rail system of electrification is unrelated to the third
rail used in
dual-gauge railways.
Description
Third rail systems are a means of providing electric traction power
to railway trains, and they use an additional rail (called a
"conductor rail") for the purpose. On most systems, the conductor
rail is placed on the sleeper ends outside the running rails, but
in some cases a central conductor rail is used. The conductor rail
is supported on ceramic insulators or insulated brackets, typically
at intervals of 10 feet (3 metres) or so.
The trains have metal contact blocks called "shoes" which make
contact with the conductor rail. The traction current is returned
to the generating station through the running rails. The conductor
rail is usually made of high conductivity steel, and the running
rails have to be electrically connected using wire bonds or other
devices, to minimise resistance in the electric circuit.
The conductor rails have to be interrupted at level crossings and
at crossovers, and ramps are provided at the ends of the sections
to give a smooth transition to the train shoes.
There is considerable diversity about the contact position between
the train and the rail; some of the earliest systems used top
contact, but developments used side or bottom contact, which
enabled the conductor rail to be covered, protecting track workers
from accidental contact and protecting the conductor rail from snow
and leaf fall.
Benefits and disadvantages of third-rail systems
Electric traction systems (where electric power is generated at a
remote power station and transmitted to the trains) are
considerably more cost-effective than diesel or steam units, where
the power unit is carried on the train. This advantage is
especially marked in urban and rapid transit systems with a high
traffic density.
So far as first cost is concerned, third-rail systems are
relatively cheap to install, compared to overhead wire contact
systems, as no structures for carrying the overhead contact wires
are required, and there is no need to reconstruct overbridges to
provide clearances. There is much less visual intrusion on the
environment.
However as third rail systems present the hazard of electric shock,
higher system voltages (above 1500 v) are not feasible. Very
high currents are therefore used, resulting in considerable power
loss in the system, and requiring relatively closely spaced feed
points (sub-stations).
The presence of an electrified rail also makes it extremely
dangerous for a person to fall into the tracks. This, however, can
be avoided using
platform screen
doors.
Furthermore, third rail systems must either be fully
grade-separated, or, if they operate at-grade, they must implement
some kind of mechanism to effectively stop pedestrians from walking
onto the tracks at grade crossings.
A famous 1992 Supreme Court of
Illinois
decision affirmed a $1.5 million verdict against
the Chicago Transit
Authority for failing to stop an intoxicated Korean immigrant
from walking onto the tracks at a grade crossing and attempting to
urinate on the third rail.
The end ramps of conductor rails (where they are interrupted, or
change sides) present a practical limitation on speed due to the
mechanical impact of the shoe, and 160 km/h (100 mph) is
considered the upper limit of practical third-rail operation. The
world speed record for a third rail train is 174 km/h
(108 mph) attained on 11 April 1988 by a British
Class 442 EMU.
Third rail systems using top contact are prone to accumulations of
snow, and ice formed from refrozen snow, and this can interrupt
operations. Some systems operate dedicated de-icing trains to
deposit an oily fluid on the conductor rail to prevent the
build-up.
Because of the gaps in the conductor rail (at level crossings and
crossovers) it is possible for a train to stop in a position where
all of its shoes are in gaps, so that no traction power is
available. The train is said to be "gapped". In these circumstances
a following train is brought up behind the stranded train to push
it on to the conductor rail. On some systems this prevents the
running of very short trains (which have fewer shoes).
History
Third-rail electrification systems are, apart from on-board
batteries, the oldest means of
supplying electric power to
trains on railways
using their own corridors, particularly in cities. Overhead power
supply was initially almost exclusively used on tramway-like
railways, though it also appeared slowly on mainline systems.
An experimental electric train using this method of power supply
was developed by the German firm of
Siemens
& Halske and shown at the
Berlin Industrial Exhibition
of 1879, with its third rail between the running rails.
Some early
electric railways used the running rails as the current conductor,
as with the 1883-opened Volk's Electric Railway
in Brighton. It was given an additional
power rail in 1886, and is still operating. The
Giant's Causeway Tramway followed,
equipped with an elevated outside third rail in 1883, later
converted to overhead wire. The first railway to use the central
third rail was the
Bessbrook
and Newry Tramway in Ireland, opened in 1885 but now, like the
Giant's Causeway line, closed. Also in the 1880s third-rail systems
began to be used in
public urban
transport. Trams were first to benefit from it: they used
conductors in conduit below the road surface (see
Conduit current collection),
usually on selected parts of the networks. This was first tried in
Cleveland (1884) and in Denver (1885) and later spread to many big
tram networks (e.g.
Manhattan, Chicago, Washington DC, London,
Paris, all closed) and Berlin (the third rail system in the city
was abandoned in the first years of the 20th century after heavy
snowfall.) The system was tried in the beachside resort of Blackpool
, UK but was soon abandoned as sand and saltwater
was found to enter the conduit and cause breakdowns, and there was
a problem with voltage drop. Some sections of tramway track
still have the slot rails visible.
A third rail supplied power to the world's first electric
underground railway, the
City & South London
Railway, which opened in 1890 (now part of the
Northern Line of the London Underground). In
1893 the world's second third-rail powered city railway opened in
Britain, the
Liverpool
Overhead Railway (closed 1956 and dismantled). The first US
third-rail powered city railway in revenue use was the 1895
Metropolitan West Side
Elevated, which soon became part of the
Chicago 'L'. In 1901,
Granville Woods, a prominent
African-American inventor, was granted a , covering various proposed
improvements to third rail systems. This has been cited to claim
that he invented the third rail system of current distribution.
However,
by that time there had been numerous other patents for electrified
third-rail systems, including Thomas
Edison's of 1882, and third rails had been in successful use
for over a decade, in installations including the rest of Chicago
'elevateds', as well as these in Brooklyn
, New York
(if not to mention the development outside the US). To what
extent Woods' ideas were adopted is thus a matter of
controversy.
[43235]
In Paris,
third rail appeared in 1900 in the main-line tunnel connecting the
Gare
d'Orsay
to the rest of the CF Paris-Orléans
network. Main-line third rail electrification was later
expanded to some suburban services.
Top contact third rail (see below) seems to be the oldest form of
power collection.
Railways pioneering in using other less
hazardous types of third rail were the New York Central Railroad on the
approach to its NYC's Grand Central Terminal
(1907 — another case of a third-rail mainline
electrification), Philadelphia's Market Street Subway-Elevated (1907),
and the Hochbahn in Hamburg (1912) —
all had bottom contact rail. However, the Manchester-Bury
Line of the
Lancashire & Yorkshire
Railway tried side contact rail in 1917. These technologies
appeared in wider use only at the turn of the 1920s and in the
1930s on, e.g., large-profile lines of the
Berlin U-Bahn, the
Berlin S-Bahn and the
Moscow Metro. The Hamburg S-Bahn has used a
side contact third rail at 1200 V DC since 1939.
In 1956 the world's first rubber-tyred railway line, Line 11 of
Paris Metro, opened. The conductor rail
evolved into a pair of guiding rails required to keep the bogie in
proper position on the new type of track. This solution was
modified on the 1971 Namboku Line of
Sapporo Subway, where a centrally placed
guiding/return rail was used plus one power rail placed laterally
as on conventional railways (see
photo).
The third rail technology at street tram lines has recently been
revived in the
new system of
Bordeaux (2004). This is a completely new technology (see
below).
Third rail is not obsolete. There are, however, countries
(particularly Japan, South Korea, India, Spain) more eager to adopt
overhead wiring to their urban
railways. But in the same time there were (and still are) many new
third rail systems built elsewhere, including technologically
advanced countries (e.g.
Copenhagen
Metro,
Taipei Metro,
Wuhan Metro). Bottom powered railways (it may be
too specific to use the term 'third rail') are also usually those
having rubber-tyred trains, whether it is a heavy metro (except two
other lines of
Sapporo Subway) or a
small capacity
people mover (PM).
Practically the type of railways where third rail is no longer used
in new systems is regional and long distance rail, which require
higher speeds and voltages.
Running rails for power supply
The first idea for feeding electricity to a train from an external
source was by using both rails on which a train runs, whereby each
rail is a conductor for each pole insulated by the sleepers.This
method is used by most model trains, however it does not work so
well for large trains as the sleepers are not good insulators,
furthermore the use of insulated wheels or insulated axles is
required. As most insulation materials have worse static properties
compared with metals used for this purpose, this results in a less
stable train vehicle.Nevertheless, it was sometimes used at the
beginning of the development of electric trains. The following
systems used it:
Some trains used for rides for children at beer festivals also use
this method for power supply.
Technical aspects
The third rail is usually located outside the two running rails,
but occasionally between them. The electricity is transmitted to
the train by means of a sliding shoe, which is held in contact with
the rail. On many systems an insulating cover is provided above the
third rail to protect employees working near the track; sometimes
the shoe is designed to contact the side (called side running) or
bottom (called bottom running) of the third rail, allowing the
protective cover to be mounted directly to its top surface. When
the shoe slides on top, it is referred to as top running. When the
shoe slides on the bottom it is not affected by the build-up of
snow or leaves.
As with overhead wires, the return current usually flows through
one or both running rails, and leakage to ground is not considered
serious. Where trains run on rubber tyres, as on parts of the
Paris Métro,
Mexico City Metro and
Santiago Metro, and on all of the
Montreal Métro, live guide bars must be
provided to feed the current. The return is effected through the
rails of the conventional track between these guide bars (
see
rubber-tyred metro). Another
design, with a third rail (current feed, outside the running rails)
and fourth rail (current return, half way between the running
rails), is used by a few steel-wheel systems, see
fourth rail. The
London Underground is the largest
of these, see
railway
electrification in Great Britain.
On line M1 of the
Milan Metro the third
rail is used as the return electrical line (with potential near the
ground) and the live electrical connection is made with a sliding
block on the side of the car contacting an electrical bar parallel
to the track approximately 1 m (3') above rail level. In this
manner there are four rails. In the northern part of the line the
more common
overhead line system is
used.
The third rail is an alternative to
overhead lines that transmit power to trains
by means of
pantograph attached to
the trains. Whereas overhead-wire systems can operate at
25 kV or more, using
alternating current (AC), the smaller
clearance around a live rail imposes a maximum of about 1200 V
(
Hamburg S-Bahn), and
direct current (DC) is used. Trains on some
lines or networks use both power supply modes (cf. below,
"Compromise systems").
One method for reducing current losses (and thus increase the
spacing of feeder/sub stations, a major cost in third rail
electrification) is to use a composite conductor rail of a hybrid
aluminium/steel design. The aluminium is a better conductor of
electricity, and a running face of stainless steel gives better
wear.
There are several ways of attaching the stainless steel to the
aluminium. The oldest is a co-extruded method, where the stainless
steel is extruded with the aluminium. This method has suffered, in
isolated cases, from de-lamination (where the stainless steel
separates from the aluminium); this is said to have been eliminated
in the latest co-extruded rails. A second method is an aluminium
core, upon which two stainless steel sections are fitted as a cap
and linear welded along the centre line of the rail. Because
aluminium has a higher
coefficient of thermal
expansion than steel, the aluminium and steel must be
positively locked to provide a good current collection interface. A
third method rivets aluminum bus strips to the web of the steel
rail. The photo below-right depicts such a rail.
Compromise systems
Several systems use third rail for part of the system, and other
systems such as overhead
catenary or
diesel power for the remainder. These may exist because of the
connection of separately-owned railways using the different
systems, local ordinances, or other historical accidents.
USA
In
New York
City
, electric trains that must use the third rail
leaving Grand Central
Terminal
on the former New York Central Railroad (now
Metro-North Railroad) switch to
overhead lines at Pelham when they
need to operate out onto the former New York, New Haven
and Hartford Railroad (now Metro North's New Haven Line) line to Connecticut
. The switch is made "on the fly" controlled
from the engineer's position.
Also in New York City where diesel exhaust would pose a health
hazard in underground station areas,
Metro-North,
Long Island Rail Road and
Amtrak use diesel locomotives that can also be
electrically powered by third-rail. This kind of locomotive (for
example the
P32AC-DM or the EMD/Siemens
built
DM30AC of LIRR), can transition between
the two modes while underway. The third-rail auxiliary system is
not as powerful as the diesel engine, so on open-air (non-tunnel)
trackage run the engines typically run in diesel mode, even where
third rail power is available. This does not hold true for the
DM30ACs, where the electric mode is much more powerful than the
diesel .
In
Manhattan
, New York City, and in Washington, D.C.
, local ordinances required electrified street
railways to draw current from a third rail and return the current
to a fourth rail, both installed in a continuous vault underneath
the street and accessed by means of a collector that passed through
a slot between the running rails. When streetcars on such
systems entered territory where
overhead
lines were allowed, they stopped over a pit where a man
detached the collector (
plow) and the
motorman placed a
trolley
pole on the overhead.
Some sections of the former London
tram system
also used the conduit current
collection system, also with some tramcars that could collect
power from both overhead and under-road sources.
The
Blue Line of Boston's
MBTA uses third
rail electrification from the start of the line downtown to
Airport
, where it switches to overhead catenary for the
remainder of the line to Wonderland
. The
Orange
Line's Hawker Siddeley 012000
series rapid transit cars (essentially a longer version of the Blue
Line's 0600's) recently had their pantograph mounting points
removed during a maintenance program; these mounts would have been
used for pantographs which would have been installed had the Orange
Line been extended.
Dual power supply method was also used on some US
interurban railways that made use of newer third
rail in suburban areas, and existing overhead streetcar (trolley)
infrastructure to reach downtown, for example the
Skokie Swift in Chicago.
United Kingdom

Eurostar on third rail near
London
Several types of British trains have been able to operate on both
overhead and third rail systems, including class
British Rail Class 313,
319,
325,
365,
375/6,
377/2,
378,
373 and
395 EMUs, plus
Class 92 locomotives.
High Speed 1
The
Class 373 used for
international services operated by Eurostar
via the Channel
Tunnel
uses overhead collection at 25
kV AC for most of its journey, with sections of 3kV DC or 1.5kV
DC on the Continent. As originally delivered, the Class 373
units were additionally fitted with 750 V DC collection
shoes, designed for the journey in London via the suburban commuter
lines.
A
switch between third-rail and overhead collection was performed
whilst running at speed, initially at Continental Junction near
Folkestone, and later on at Fawkham Junction
after the opening of the first section of the
Channel Tunnel Rail
Link. Between Kensington
Olympia railway station
and North Pole depot
further switchovers were necessary.
The dual system caused some problems when drivers forgot to switch
between modes. Failure to retract the shoes when entering France
caused severe damage to some trackside equipment, leading to SNCF
installing a concrete block at the Calais entrance to the Channel
Tunnel to break the 3rd rail shoe off if it wasn't retracted. On
the other hand, an accident occurred in the UK when a Eurostar
driver failed to retract the pantograph before entering the 3rd
rail system, leading to a low signal gantry and the pantograph
being destroyed.
On 14
November 2007, Eurostar's passenger operations were transferred to
St Pancras
railway station
and maintenance operations to Temple Mills depot deprecating the
requirement for the 750DC third rail collection equipment and
leading to its removal from the fleet.
In 2009,
Southeastern began
operating domestic services over High Speed 1 from St Pancras using
its new
Class 395 EMUs. These
services operate on the high speed line as far as , before
transferring to the classic lines to serve north and mid Kent. As a
consequence, these trains are dual voltage enabled as the majority
of the routes they will operate over are third rail
electrified.
North London Line
In
London, the North London Line
changes its power supply several times between Richmond
and Stratford
stations.
Thameslink
The route was originally third rail throughout but a number of
technical electrical earthing problems, plus part of the route also
being covered already by overhead electric wires provided for
electrical-hauled freight and
Regional
Eurostar services led to the change.
The cross-city
Thameslink service runs on the Southern
Region third rail network from Farringdon station
southwards and on overhead line northwards from
Farringdon to Bedford
. The changeover is made whilst stationary at
Farringdon.
Northern City
On the
Moorgate to Hertford and Welwyn suburban service routes, the
East Coast Main Line sections
are 25 kV AC, with a changeover at Drayton Park
railway station
because of the size of the tunnels leading to
Moorgate
station
are too small to allow overhead
electrification.
Continental Europe
The older lines in the west of the
Oslo
T-bane system were built with overhead lines (some since
converted to third rail) while the eastern lines were built with
third rail. Trains operating on the older lines can operate both
with third rail and overhead lines. To mitigate investment costs,
the
Rotterdam Metro, basically a
third-rail powered system, has been given some outlying branches
built on surface as
light rail (called
'Sneltram' in Dutch), with numerous level crossings protected with
barriers and traffic lights. These branches have overhead wires.
Similarly, in Amsterdam one 'Sneltram' route goes on
Metro tracks and passes to surface alignment
in the suburbs, which it shares with standard trams. In most recent
developments, the
RandstadRail project
also requires Rotterdam Metro trains to run under wires on their
way along the former mainline railway to The Hague.
The new
tramway in Bordeaux
(France
) uses a
novel system with a third rail in the center of the track.
The third rail is separated into 8 m (26 ' 3 ")
long conducting and 3 m (9 ' 10 ") long
isolation segments. Each conducting segment is attached to an
electronic circuit which will make the segment live once it lies
fully beneath the tram (activated by a coded signal sent by the
train) and switch it off before it becomes exposed again. This
system (called "
Alimentation par
Sol" (APS), meaning "current supply via ground") is used in
various locations around the city but especially in the historic
centre: elsewhere the trams use the conventional
overhead lines, see also
ground-level power supply. In
summer 2006 it was announced that two new French tram systems would
be using APS over part of their networks.
These will be
Angers
and Reims
, with both
systems expected to open around 2009–2010.
The
French Fréjus line to Modane
was
electrified with 1500 V DC third rail, later converted to overhead
wires at the same voltage. Stations had overhead wires from
the beginning.
Conversions
Despite various technical possibilities of operating stock with
dual power collecting modes, the desire to achieve full
compatibility of entire networks seems to have been the decisive
cause of conversions from third rail to overhead supply (or vice
versa).
Suburban
corridors in Paris from Gare Saint-Lazare
, Gare des Invalides
(both CF Ouest) and
Gare
d'Orsay
(CF PO), were
electrified from 1924, 1901, 1900 respectively. They all
changed to overhead wires by stages after they became part of a
wide scale electrification project of the
SNCF
network in the 1960s–70s.
In Manchester area, the
L&YR line was first
electrified with overhead wires (1913), then changed to third rail
(1917, cf.
Railway electrification
in Great Britain) and again in 1992 to overhead wires in the
course of its adaptation for the
Manchester Metrolink. Trams in city
centre streets, carrying collector shoes projecting from their
bogies, were considered too dangerous for pedestrians and motor
traffic to attempt dual-mode technology (in Amsterdam and Rotterdam
Sneltram vehicles go out to surface in suburbs, not in
busy central areas).
The same thing happened to the West Croydon
— Wimbledon Line in Greater London (originally electrified by the
Southern Railway) when
Tramlink
was opened in 2000.
Three lines of five making up the core of
Barcelona Metro network changed to overhead
power supply from third rail. This operation was also done by
stages and completed in 2003.
The opposite took place in south London. The South London Line of
the
LBSCR
network between Victoria and London Bridge was electrified with
catenary in 1909.
The system was later extended to Crystal
Palace, Coulsdon North
and Sutton. In the course of main-line third
rail electrification in south-east England, the lines were
converted by 1929.
The first overhead electric trains appeared on the
:de:Hamburg-Altonaer
Stadt- und Vorortbahn in 1907. Thirty years later, the
main-line railway operator,
Deutsche
Reichsbahn, influenced by the success of the third-rail
Berlin S-Bahn, decided to switch what
was now called
Hamburg S-Bahn to
third rail. The process began in 1940 and was not finished until
1955.
In 1976–1981 the third-rail
Viennese
U-Bahn U4 Line substituted the Donaukanallinie and Wientallinie
of the
Stadtbahn, built
c1900 and first electrified with overhead wires in 1924. This was
part of a big project of consolidated U-Bahn network construction.
The other electric
Stadtbahn line, whose conversion into
heavy rail stock was rejected, still operates under wires with
light rail cars (as U6), though it has been thoroughly modernised
and significantly extended. As the platforms on the Gürtellinie
were not suitable for raising without much intervention into
historic
Otto Wagner's station
architecture, the line would anyway remain incompatible with the
rest of the U-Bahn network. Therefore an attempt of conversion to
third rail would have been pointless. In Vienna, paradoxically, the
wires were retained for aesthetic (and economic) reasons.
The western portion of the
Skokie Swift of the
Chicago 'L' changed from catenary wire
to third rail in 2004, making it fully compatible with the rest of
the system.
The reasons for building the overhead powered
Tyne & Wear Metro network roughly
on lines of the long-gone third-rail
Tyneside Electrics system in Newcastle
area are likely to have roots in economy and psychology rather than
in the pursuit of compatibility. At the time of the Metro opening
(1980) there were no third-rail light rail vehicles on the market
and the latter technology was confined to much more costly heavy
rail stock. Also the far-going change of image was desired: the
memories of the last stage of operation of the Tyneside Electrics
were far from being favourable. This was the construction of the
system from scratch after 11 years of ineffective diesel
service.
Highest voltages
In Germany during the Third Reich a railway system with 3 metres
gauge width was planned. For this railway system electrification
with a voltage of 100 kV taken from a third rail was considered, in
order to avoid destruction of overhead wires by anti-aircraft guns.
However such a power system would not have worked as it is not
possible to insulate a third rail for such high voltages in the
proximity of the rails and the whole project did not progress any
further because of World War II.
Simultaneous use with overhead wire
A railway can be electrified with an overhead wire and a third rail
at the same time. This was the case, for example, on the Hamburg
S-Bahn between 1940 and 1955. A modern example is Birkenwerder
Railway Station near Berlin, which has third rail on both sides and
overhead wire.
The whole Penn
Station
complex in New York City is also electrified with
both systems. However, such systems have problems with the
influence of the different supplies. If one supply is DC and the
other AC, an undesired premagnetization of the AC transformers can
occur. For this reason,
double
electrification is usually avoided.
The border station of Modane on the French-Italian
Fréjus railway was electrified at both
1500 V DC third rail for French trains and with overhead wires
(initially three-phase, later 3000 V DC) for Italian trains. When
the French part of the line was converted to overhead wires, the
voltage of the wires was dropped to 1500 V DC. Now Italian trains
run in Modane feed with 1500 V DC instead of 3000, with half of
their power.
Technical advances lower running costs
The introduction of
supercapacitors
has promised to drop electrical running costs for trains running on
third rail and overhead wires. Kinetic braking energy is clawed
back by storing electrical energy in supercapacitors stored onboard
the vehicle. The vehicle is braked by magnets. This stored energy
is then used when starting up the train, when high currents are
used. The supplementing supercapacitors reduce current draw through
the electrical pickup on accelerating at train startup. The
electrical storage buffering supercapacitors reduces the current
draw putting less strain on the electrical system.
Claimed energy reduction is around 30%. Electric railway systems
can be more competitive and a real economical alternative to the
car.
The technology can be used equally well for diesel electric
locomotives, where 25% to 40% reduction in energy consumption is
claimed, however only onboard location of supercapacitor banks is
feasible. This technology equally applies to road vehicles that use
electric motors for propulsion, such as hybrid cars and busses. Any
electrical equipment that requires regular braking can reduce
operating costs using supercapacitors. Reduced operating costs of
elevators on underground railways would be a great benefit to
operators and adding to the economic competitiveness to other
transport modes.
A further welcome knock on effect is that emissions from power
generating plant and diesel-electric locomotives will be less,
giving environmental benefits.
Since 2003 Mannheim Stadtbahn in Mannheim, Germany has operated a
light-rail vehicle using electric double-layer supercapacitors to
store braking energy.
A number of companies are developing electric double-layer
supercapacitor technology.
Siemens AG is
developing mobile energy storage based on double-layer
supercapacitors called Sibac Energy Storage Sitras SES, are
developing stationary trackside version . The company Cegelec is
also developing an electric double-layer capacitor-based energy
storage system .
In model trains
In
1906, the
Lionel
electric trains became the first model trains to use a
third rail to power the
locomotive. Lionel track uses a third rail in the center, while the
two outer rails are electrically connected together. This solved
the problem two-rail model trains have when the track is arranged
to loop back on itself, as ordinarily this causes a short-circuit.
(Even if the loop was gapped, the locomotive would create a short
and stop as it crossed the gaps.) Lionel electric trains also
operate on alternating current. The use of alternating current
means that a Lionel locomotive cannot be reversed by changing
polarity; instead, the locomotive sequences among several states
(forward, neutral, backward, for example) each time it is started.
Märklin three-rail trains use a short spike of DC voltage to
reverse a relay within the locomotive while it is stopped.
Märklin's track does not have an actual third rail, instead, a
series of short pins provide the current, taken up by a long "shoe"
under the engine. This shoe is long enough to always be in contact
with several pins.
Most model train sets today use only two rails, and supply
locomotives with direct current. The voltage and polarity of the
current controls the speed and direction of the train. A growing
exception is
Digital Command
Control (DCC), where bi-polar DC is delivered to the rails at a
constant voltage, along with digital signals that are decoded
within the locomotive; the signals carry addresses that indicate
which locomotive is being commanded when multiple locomotives are
present on the same track.
Some model railroads realistically mimic the third rail
configurations of their full-sized counterparts; such models may or
may not actually draw power from the third rail (most do
not).
List of systems
See List of rail
transport systems using third rail for a complete
list.
See also
Notes
External links